What is the Required Code to Complete Load Bank Testing?

For contractors and building engineers responsible for maintaining commercial generators, load bank testing is a crucial task that ensures reliable operation when the generator is needed most. But to conduct this testing properly, it’s essential to adhere to specific codes and standards. So, what exactly are the required codes to complete load bank testing?

NFPA 110: Standard for Emergency and Standby Power Systems

The primary code governing load bank testing for generators is the National Fire Protection Association (NFPA) 110, which focuses on the performance of emergency and standby power systems. It outlines testing frequencies, processes, and criteria for various generator components.

Key Requirements from NFPA 110

  1. Testing Frequency: For Level 1 and Level 2 systems (critical systems like hospitals or data centers), the code requires testing of the entire generator system under load at least once every three years. The monthly testing under normal operating load isn’t enough; full load bank testing ensures that the generator can handle its maximum rated load.
  2. Duration of Testing: Load bank testing should last for a minimum of **2 hours**, with the generator running at 30% load for the first 30 minutes, followed by 50% load for another 30 minutes, and then 100% load for the final hour. This gradual increase in load is crucial to test the full capacity of the generator and identify any operational weaknesses.
  3. Simulating Actual Loads: NFPA 110 emphasizes testing generators with the actual loads they are expected to handle in real-world conditions. However, load banks can be used when the actual facility loads are insufficient to meet the required testing parameters.

NFPA 99: Healthcare Facilities

For contractors working in healthcare settings, NFPA 99 governs the electrical systems, including generator testing requirements. It specifically addresses load bank testing in hospitals, nursing homes, and other healthcare facilities where reliable power is critical for life support and other essential systems.

NFPA 99 Load Bank Testing Details

  • Annual Testing: Generators in healthcare settings are subject to more frequent testing than standard commercial installations. NFPA 99 calls for annual testing under load, using either the facility’s real load or a portable load bank.
  • 90-Minute Test: Unlike NFPA 110, NFPA 99 mandates a continuous 90-minute test under load, starting with a higher percentage of the rated capacity.

Local Building Codes and Regulations

While NFPA standards provide national guidelines, local jurisdictions often have their own additional regulations. These may require more frequent testing or additional documentation and reporting after each test. Always consult local building codes or the Authority Having Jurisdiction (AHJ) to confirm compliance.

What Happens During Load Bank Testing?

Load bank testing simulates the electrical load a generator will need to handle in an actual emergency. The test verifies that the generator can not only start up and run but also maintain consistent output under heavy demand. It also ensures that the cooling system is functioning properly, and that the engine and electrical components are working efficiently under stress.

During the test, a contractor or building engineer connects a load bank to the generator. The load is gradually increased, pushing the generator to operate at different levels, as specified by the relevant code. After the test, you’ll receive data on the generator’s performance, including fuel efficiency, exhaust temperature, and electrical output.

Conclusion

Staying up to code for load bank testing involves a careful balance of national standards like NFPA 110, industry-specific guidelines like NFPA 99, and local regulations. For contractors and building engineers, understanding and adhering to these codes is essential to ensure the reliability of backup power systems. Regular testing not only keeps your clients compliant but ensures their generators will function in an emergency, protecting their operations and, in some cases, lives.

For more information on generator load bank testing requirements, request a quote or give us a call at 1-800-899-3931